(1) Projects that fall under Schedule 1 require an environmental impact assessment, and regulations 8 to 16 apply.
(2) For projects that fall under Schedule 2—
(a) the developer must apply to the Secretary of State for a direction as to whether an environmental impact assessment is required (“a screening direction”) and the Secretary of State must serve a screening direction in accordance with regulation 6; or
(b) the developer may choose that the project undergoes an environmental impact assessment, and regulations 8 to 16 apply.
(3) Projects that fall under Schedule 3 do not require an environmental impact assessment where the Secretary of State considers that the project is not likely to have a significant effect on the environment pursuant to regulation 7.
(4) Projects do not require an environmental impact assessment where the Secretary of State directs this under regulations 17 and 18 (exempt projects).
(5) Where a project requires both an environmental impact assessment under these Regulations and an assessment under either regulation 5 of the Offshore Petroleum Activities (Conservation of Habitats) Regulations 2001 or regulation 28 of the Conservation of Offshore Marine Habitats and Species Regulations 2017 , the Secretary of State must ensure that the preparation of those assessments is coordinated where appropriate.

---
Source: https://www.legislation.gov.uk/uksi/2020/1497/regulation/5 (the official version)
Page: https://openlegislation.uk/offshore-oil-and-gas-exploration-production-unloading-and-storage-environmental-impact-assessment-regulations-2020/regulation-5
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.