# The Offshore Oil and Gas Exploration, Production, Unloading and Storage (Environmental Impact Assessment) Regulations 2020, Paragraph 1

Extent: E+W+S+N.I.

A description of the project comprising information on the site, design, size and other relevant features of the project including—
(a) a description of the location of the project;
(b) a description of the physical characteristics of the project, including any demolition works necessary to implement the project, and the land-use requirements during the construction and operational phases;
(c) a description of the main characteristics of the operational phase of the project, in particular any production process, which must cover energy demand and energy used, and nature and quantity of the materials and natural resources used (including water, land, soil and biodiversity);
(d) an estimate, by type and quantity, of expected residues and emissions (such as water, air, soil and subsoil pollution, noise, vibration, light, heat and radiation) and quantities and types of waste produced during the construction and operation phases.

---
Source: https://www.legislation.gov.uk/uksi/2020/1497/schedule/6/paragraph/1 (the official version)
Page: https://openlegislation.uk/offshore-oil-and-gas-exploration-production-unloading-and-storage-environmental-impact-assessment-regulations-2020/schedule-6/paragraph-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.