(1)

Part 1 of the 1965 Act (compulsory acquisition under Acquisition of Land Act 1946), as applied to this Order by section 125 (application of compulsory acquisition provisions) of the 2008 Act, is modified as follows.

(2)

In section 4A(1) (extension of time limit during challenge) for “section 23 of the Acquisition of Land Act 1981 (application to High Court in respect of compulsory purchase order)” substitute “section 118 (legal challenges relating to applications for orders granting development consent) of the Planning Act 2008”.

(3)

In section 11A (powers of entry: further notice of entry)—

(a)

in subsection (1)(a), after “land” insert “under that provision”; and

(b)

in subsection (2), after “land” insert “under that provision”.

(4)

In Schedule 2A (counter-notice requiring purchase of land not in notice to treat)—

(a)

for paragraphs 1(2) and 14(2) substitute—

“(2)

But see article 25 (acquisition of subsoil only) of the One Earth Solar Farm Order 2026, which excludes the acquisition of subsoil only from this Schedule.”; and

(b)

after paragraph 29 insert—

“PART 4

INTERPRETATION

30.

In this Schedule, references to entering on and taking possession of land do not include doing so under article 18 (protective works to buildings), article 29 (temporary use of land for constructing the authorised development) or article 30 (temporary use of land for maintaining the authorised development) of the One Earth Solar Farm Order 2026.”.