If in consequence of the agreement reached in accordance with paragraph 103(1) or the powers granted under this Order the access to any apparatus or the Chesterfield to High Marnham Project and North Humber to High Marnham Project is materially obstructed, the undertaker must provide such alternative means of access to such apparatus or to the Chesterfield to High Marnham Project and North Humber to High Marnham Project as will enable NGET Plc to maintain or use the apparatus no less effectively than was possible before such obstruction.