# The One Earth Solar Farm Order 2026, Paragraph 28: Fencing


Where so required by the engineer acting reasonably the undertaker must, to the reasonable satisfaction of the engineer, fence off a specified work or a protective work or take such other steps as the engineer may require to be taken for the purpose of separating a specified work or a protective work from the waterway, whether on a temporary or permanent basis or both.

---
Source: https://www.legislation.gov.uk/uksi/2026/934/schedule/14/paragraph/28 (the official version)
Page: https://openlegislation.uk/one-earth-solar-farm-order-2026/schedule-14/paragraph-28
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.