Paragraph 96 Interaction with the NGET Projects

Original text. Later amendments are not shown.

Without limiting any other provision of this Part of this Schedule, the undertaker must use reasonable endeavours to avoid any conflict arising between the construction, maintenance and operation of the authorised development, and the NGET Projects. For the purposes of this paragraph, “reasonable endeavours” means—

(a)

undertaking consultation on the detailed design and programming of the grid connection works and all works associated with or ancillary to the grid connection works to ensure that the design and programme for the grid connection works does not unreasonably impede or interfere with the NGET Projects;

(b)

having regard to the proposed programme of works for the NGET Projects (as may be made available to the undertaker by NGET as soon as reasonably practicable in the circumstances);

(c)

seeking to facilitate a co-ordinated approach to the programme, land assembly and the carrying out of the grid connection works and the NGET Projects;

(d)

providing a point of contact for each of the undertaker and NGET for continuing liaison and co-ordination throughout the construction and operation of the authorised development; and

(e)

keeping NGET informed of material changes to detailed design and on the programme of works for the grid connection works.