# The One Earth Solar Farm Order 2026, Paragraph 1: Interpretation


(1) In this Schedule—
“part” includes a phase, part of a phase, multiple phases or multiple parts of phases;
“phase” means a phase of the authorised development as set out in the written scheme approved pursuant to requirement 3;
“requirement consultee” means any body or authority named in a requirement as a body to be consulted by the relevant planning authority in discharging that requirement; and
“start date” means the date of the notification given by the Secretary of State under paragraph 4(2)(c).
(2) Where an application is made under this Schedule for any consent, agreement or approval required by a requirement, the application may be for all of the authorised development, or for a part of the authorised development.

---
Source: https://www.legislation.gov.uk/uksi/2026/934/schedule/15/paragraph/1 (the official version)
Page: https://openlegislation.uk/one-earth-solar-farm-order-2026/schedule-15/paragraph-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.