  "text": "(1) No part of the authorised development may commence until written details of the drainage management plan for that part have been submitted to and approved by the relevant planning authority for that part, such approval to be in consultation with Anglian Water and the Environment Agency.\n(2) The written details under sub-paragraph (1) must be substantially in accordance with the flood risk assessment and outline drainage strategy.\n(3) Any approved scheme must be implemented as approved and maintained throughout the construction and operation of the authorised development.",
  "extent": null,
  "status": null,
  "version": "current",
  "annotations": [],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2026/934/schedule/2/paragraph/11",
    "retrieved_at": "2026-10-28T20:56:15.458786+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}