Paragraph 13 Construction environmental management plan
No part of the authorised development may commence until a construction environmental management plan for that part has been submitted to and approved by the relevant planning authority for that part, such approval to be in consultation with the relevant county authority for that part as the local highway authority and waste planning authority, the Environment Agency, and Anglian Water in relation to water resources.
The construction environmental management plan must be substantially in accordance with the outline construction environmental management plan.
All construction works associated with the authorised development must be carried out in accordance with the approved construction environmental management plan.
The construction management plan must include a commitment to regularly share all relevant pre-construction, construction, post-construction and operation survey and monitoring data in the appropriate formats with the relevant Local Environmental Records Centre(s) and relevant national and regional recording schemes.
For the purposes of sub-paragraph (1), “commence” includes part (d) (remedial works in respect of any contamination or other adverse ground conditions) and part (i) (Work No. 7 (works to facilitate access to Work Nos. 1 to 6 and 8)) of the permitted preliminary works.