Paragraph 19 Soil management plan

Original text. Later amendments are not shown.

(1)

No part of the authorised development may commence until a soil management plan for that part has been submitted to and approved by the relevant planning authority for that part.

(2)

The soil management plan must be substantially in accordance with the outline soil management plan.

(3)

The soil management plan must be implemented as approved and maintained throughout the construction, operation and decommissioning of the relevant part of the authorised development to which the plan relates.