Paragraph 3 Phasing of the authorised development and date of final commissioning
The authorised development may not commence until a written scheme setting out the phase or phases of construction of the authorised development has been submitted to and approved by the relevant planning authorities, such approval to be in consultation with the relevant county authorities.
The scheme submitted and approved pursuant to sub-paragraph (1) must include a timetable for the construction of the phases of the authorised development and a plan identifying the phasing areas.
The scheme submitted and approved pursuant to sub-paragraph (1) must be implemented as approved.
Notice of the date of final commissioning with respect to each phase of Work No. 1 must be given to the relevant planning authorities for each phase within 15 working days of the date of final commissioning for that phase.