# The One Earth Solar Farm Order 2026, Paragraph 1: Interpretation


In this Schedule—
“access rights” means rights over land to—
(a) alter, improve, form, maintain, retain, use (with or without vehicles, plant and machinery), remove, reinstate means of access to the authorised development including visibility splays and road widening or improvements and to remove impediments (including vegetation) to such access; and
(b) pass and repass on foot, with or without vehicles, plant and machinery (including rights to lay and use any temporary surface) for all purposes in connection with the authorised development;
“cable rights” means rights over land to—
(a) install, use, support, protect, inspect, alter, remove, replace, retain, renew, improve and maintain electrical underground cables, earthing cables, optical fibre cables, data cables, telecommunications cables and other services, works associated with such cables including bays, ducts, protection and safety measures and equipment, and other apparatus and structures;
(b) remain, pass and repass on foot, with or without vehicles, plant and machinery (including rights to lay and use any temporary surface or form a temporary compound) for all purposes in connection with the authorised development; and
(c) restrict and remove the erection of buildings or structures, restrict the altering of ground levels, restrict and remove vegetation and restrict the planting of trees or carrying out operations or actions (including but not limited to blasting and piling) which may obstruct, interrupt or interfere with the exercise of the rights or damage the authorised development;
“rights for the purpose of Work No. 5” means—
(a) cable rights;
(b) vegetation maintenance rights;
(c) rights over land to install, use, support, protect, inspect, alter, remove, replace, refurbish, reconstruct, retain, renew, improve and maintain security fencing, gates, boundary treatment, public rights of way, access tracks and other means of access, and any other ancillary apparatus and any other works as necessary; and
(d) rights over land to install, use, support, protect, inspect, alter, remove, replace, refurbish, reconstruct, retain, renew, improve and maintain sewers, drains, pipes, ducts, mains, conduits, services, flues and to drain into and manage waterflows in any drains, watercourses and culverts;
“substation connection rights” means, within a corridor of up to 20 metres in width, rights over land to—
(a) install, use, support, protect, inspect, alter, remove, replace, retain, renew, improve and maintain electrical cables, earthing cables, optical fibre cables, data cables, telecommunications cables and other services, works associated with such cables including bays, ducts, protection and safety measures and equipment, and other apparatus and structures and to connect such cables and services to the National Grid High Marnham Substation;
(b) install, use, support, protect, inspect, alter, remove, replace, retain, renew, improve and maintain watercourses, public sewers and drains and drainage apparatus and equipment;
(c) remain, pass and repass on foot, with or without vehicles, plant and machinery (including rights to lay and use any temporary surface or form a temporary compound) for all purposes in connection with the National Grid High Marnham Substation works;
(d) restrict and remove the erection of buildings or structures, restrict the altering of ground levels, restrict and remove the planting of trees or carrying out operations or actions (including but not limited to blasting and piling) which may obstruct, interrupt or interfere with the exercise of the rights or damage the authorised development; and
(e) install, use, support, protect, inspect, alter, remove, replace, retain, renew, improve and maintain soft landscaping and biodiversity measures; and
“vegetation maintenance rights” means rights over land to install, use, support, protect, inspect, alter, remove, replace, retain, renew, improve and maintain vegetation and restrict or prevent the removal of vegetation for the purposes of the authorised development and in connection with the authorised development.
(1)
Plot reference number shown on the Land Plan
(2)
Purposes for which rights over land may be required and restrictive covenants imposed
01-014
rights for the purpose of Work No. 5
01-015
rights for the purpose of Work No. 5
03-001
rights for the purpose of Work No. 5
03-002
rights for the purpose of Work No. 5
03-004
substation connection rights, rights for the purpose of Work No. 5, access rights
04-002
substation connection rights, rights for the purpose of Work No. 5, access rights
04-005
substation connection rights, rights for the purpose of Work No. 5, access rights
04-009
substation connection rights, rights for the purpose of Work No. 5
04-011a
substation connection rights, rights for the purpose of Work No.5
04-011c
substation connection rights, rights for the purpose of Work No. 5
05-003
substation connection rights, rights for the purpose of Work No. 5, access rights
05-005
substation connection rights, rights for the purpose of Work No. 5, access rights
05-007
substation connection rights, rights for the purpose of Work No. 5, access rights
05-008
substation connection rights, rights for the purpose of Work No. 5
05-009
substation connection rights, rights for the purpose of Work No. 5, access rights
05-009a
substation connection rights, rights for the purpose of Work No. 5, access rights
05-010
substation connection rights, rights for the purpose of Work No. 5, access rights
05-011
substation connection rights, rights for the purpose of Work No. 5, access rights
05-011a
substation connection rights, rights for the purpose of Work No. 5, access rights
06-001
rights for the purpose of Work No. 5
06-002
substation connection rights, rights for the purpose of Work No. 5
06-003
substation connection rights, rights for the purpose of Work No. 5
06-003a
substation connection rights, rights for the purpose of Work No. 5, access rights
07-001
substation connection rights, rights for the purpose of Work No. 5, access rights
07-002
substation connection rights, rights for the purpose of Work No. 5
07-003
rights for the purpose of Work No. 5
07-004
rights for the purpose of Work No. 5
07-005
substation connection rights, rights for the purpose of Work No. 5, access rights
07-008
rights for the purpose of Work No. 5
07-010
substation connection rights, rights for the purpose of Work No. 5, access rights
07-010a
substation connection rights, rights for the purpose of Work No.5
07-011
substation connection rights, rights for the purpose of Work No. 5, access rights
07-013
substation connection rights, rights for the purpose of Work No. 5, access rights
07-013a
substation connection rights, rights for the purpose of Work No. 5, access rights
07-014
substation connection rights, rights for the purpose of Work No. 5
07-015
substation connection rights, rights for the purpose of Work No. 5, access rights
08-001
substation connection rights, rights for the purpose of Work No. 5
08-002
substation connection rights, rights for the purpose of Work No. 5
08-003
substation connection rights, rights for the purpose of Work No. 5
08-004
substation connection rights, rights for the purpose of Work No. 5
08-005
substation connection rights, rights for the purpose of Work No. 5
08-006
substation connection rights, rights for the purpose of Work No. 5
08-007
substation connection rights, rights for the purpose of Work No. 5
08-008
substation connection rights, rights for the purpose of Work No. 5
08-009
substation connection rights, rights for the purpose of Work No. 5
08-010
substation connection rights, rights for the purpose of Work No. 5
08-011
substation connection rights, rights for the purpose of Work No. 5
10-002
rights for the purpose of Work No. 5, access rights
10-005
substation connection rights, rights for the purpose of Work No. 5, access rights
11-007
rights for the purpose of Work No. 5
11-008
rights for the purpose of Work No. 5
11-009
rights for the purpose of Work No. 5
12-005
substation connection rights, rights for the purpose of Work No. 5
12-009
rights for the purpose of Work No. 5
14-004
rights for the purpose of Work No. 5
14-005
rights for the purpose of Work No. 5
14-006
rights for the purpose of Work No. 5
14-007
rights for the purpose of Work No. 5
14-008
rights for the purpose of Work No. 5
14-012
rights for the purpose of Work No. 5, access rights
14-015
rights for the purpose of Work No. 5
14-017
rights for the purpose of Work No. 5
14-018
rights for the purpose of Work No. 5
14-019
rights for the purpose of Work No. 5
14-027
rights for the purpose of Work No. 5
15-001
rights for the purpose of Work No. 5
15-006
rights for the purpose of Work No. 5
15-007
rights for the purpose of Work No. 5
15-008
rights for the purpose of Work No. 5
15-009
rights for the purpose of Work No. 5
15-012
rights for the purpose of Work No. 5
15-013
rights for the purpose of Work No. 5
15-014
rights for the purpose of Work No. 5
15-015
rights for the purpose of Work No. 5
15-016
rights for the purpose of Work No. 5
15-017
rights for the purpose of Work No. 5
15-018
rights for the purpose of Work No. 5
16-001
rights for the purpose of Work No. 5, access rights
16-002
rights for the purpose of Work No. 5
16-005
rights for the purpose of Work No. 5, access rights
16-006
rights for the purpose of Work No. 5, access rights
16-010
rights for the purpose of Work No. 5

---
Source: https://www.legislation.gov.uk/uksi/2026/934/schedule/8/paragraph/1 (the official version)