# The Ouseburn Barrage Order 2007, Paragraph 24


Not later than 28 days before—
(a) starting to carry out any tidal work; or
(b) exercising any of the powers conferred by article 9 (power to dredge etc.),
the Council shall submit to the Port Health Authority plans thereof and such further particulars as may be available to the Council and as the Port Health Authority may reasonably require in respect of carrying out such works or in exercising such powers.

---