# The Outer Dowsing Offshore Wind Farm Order 2026, Paragraph 26: Restoration of land used temporarily for construction


Any land landward of mean low water springs within the Order limits which is used temporarily for construction of the onshore transmission works and not ultimately incorporated in permanent works or approved landscaping must be reinstated, in accordance with such details as Lincolnshire County Council in consultation with the relevant planning authority may approve, within twelve months of completion of the relevant stage of the onshore transmission works or such other period as the relevant highway authority may approve.

---
Source: https://www.legislation.gov.uk/uksi/2026/138/schedule/1/paragraph/26 (the official version)