# The Outer Dowsing Offshore Wind Farm Order 2026, Paragraph 32: Completion of construction


(1) The undertaker must submit a close out report to the MMO, MCA, UKHO, the relevant statutory nature conservation body and Trinity House within three months of the date of completion of construction. The close out report must confirm the date of completion of construction and must include the following details—
(a) the final number of installed wind turbine generators;
(b) the installed wind turbine generator parameters relevant for ornithological collision risk modelling;
(c) as built plans;
(d) latitude and longitude coordinates of the centre point of the location for each wind turbine generator and the offshore accommodation platform provided as Geographical Information System data referenced to WGS84 datum;
(e) latitude and longitude coordinates of the array cable routes provided as Geographical Information System data referenced to WGS84 datum; and
(f) the location, volume and area of cable protection.
(2) Following completion of construction, no further construction activities can be undertaken under this licence, with the exception of the deployment of cable protection.
(3) For any subsequent deployments of cable protection following completion of construction, the undertaker must submit an updated close out report not more than four months following deployment of the cable protection.

---
Source: https://www.legislation.gov.uk/uksi/2026/138/schedule/10/paragraph/32 (the official version)
Page: https://openlegislation.uk/outer-dowsing-offshore-wind-farm-order-2026/schedule-10/paragraph-32
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

