# The Outer Dowsing Offshore Wind Farm Order 2026, Paragraph 143: Coexistence and proximity agreement


If, at any time the undertaker plans to undertake the undertaker’s works or any other work which is within 500m of the Barque Assets, the undertaker shall notify the owner and the undertaker and the owner must, unless agreed otherwise, acting reasonably, agree and enter into a co-existence and proximity agreement as soon as reasonably practicable.

---
Source: https://www.legislation.gov.uk/uksi/2026/138/schedule/18/paragraph/143 (the official version)
Page: https://openlegislation.uk/outer-dowsing-offshore-wind-farm-order-2026/schedule-18/paragraph-143
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.