# The Outer Dowsing Offshore Wind Farm Order 2026, Paragraph 156: Control of works within the DEP control area


Works within Work Nos. 5, 7 and 8 must not be commenced until—
(a) Plans of the DEP Control Area have been submitted to and approved by the Secretary of State; and
(b) The undertaker has entered into the DEP Proximity Agreement with DEL,
unless otherwise agreed in writing by the undertaker and DEL.

---