# The Outer Dowsing Offshore Wind Farm Order 2026, Paragraph 172: Notices


Notwithstanding article 46 (service of notices), any plans submitted to Spalding Energy by the undertaker pursuant to paragraph 8 must be submitted by courier service, first class post or by registered post to Spalding Energy Company, Ltd, West Marsh Road, Spalding, Lincolnshire, PE11 2BB and with a copy sent to edaniels@intergen.com and uknotices@intergen.com or such other address as Spalding Energy may from time to time appoint instead for that purpose and notify to the undertaker in writing.

---
Source: https://www.legislation.gov.uk/uksi/2026/138/schedule/18/paragraph/172 (the official version)
Page: https://openlegislation.uk/outer-dowsing-offshore-wind-farm-order-2026/schedule-18/paragraph-172
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.