# The Outer Dowsing Offshore Wind Farm Order 2026, Paragraph 16: Guillemot CIMP


Where the undertaker elects to submit a Guillemot CIMP under paragraph 2(1)(b) no offshore works are to commence until a plan for the work of the GCSG has been submitted to and approved by the Secretary of State. Such plan to include—
(a) terms of Reference of the GCSG;
(b) details of the membership of the GCSG which must include the relevant statutory nature conservation body and, where appropriate, the MMO and/or the relevant planning authority as core members;
(c) details of the proposed schedule of meetings, timetable for preparation of the Guillemot CIMP and reporting and review periods; and
(d) the dispute resolution mechanism.

---