# The Peartree Hill Solar Farm Order 2026, Paragraph 30


(1) If there is any failure by the undertaker to obtain consent or comply with conditions imposed by the Agency in accordance with these protective provisions and where the Agency acting reasonably considers it necessary to avoid any of the risks specified in sub-paragraph (2), the Agency may serve written notice requiring the undertaker to cease all or part of the specified works as may be specified within the notice within such reasonable period as specified in the notice, and the undertaker must cease constructing the specified works or part thereof until such time as it has obtained the consent or complied with the condition specified within the notice served.
(2) The risks specified in sub-paragraph (1) are—
(a) risk of flooding;
(b) risk of harm to the environment;
(c) risk of detrimental impact on drainage;
(d) damage to the fishery.

---
Source: https://www.legislation.gov.uk/uksi/2026/869/schedule/11/paragraph/30 (the official version)
Page: https://openlegislation.uk/peartree-hill-solar-farm-order-2026/schedule-11/paragraph-30
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.