# The Peartree Hill Solar Farm Order 2026, Paragraph 56


Without limiting any other provision of this Part of this Schedule, the undertaker must use reasonable endeavours to avoid any conflict arising between the construction, maintenance and operation of the authorised works and the Wanlass Beck Project. For the purposes of this paragraph, “reasonable endeavours” means—
(a) undertaking consultation on the detailed design and programming of the Peartree Hill project works and all works associated with or ancillary to the Peartree Hill project works to ensure that the design and programme for the Peartree Hill Project works does not unreasonably impede or interfere with the Wanlass Beck Project;
(b) having regard to the proposed programme of works for the Wanlass Beck Project as may be made available to the undertaker by National Grid Electricity Transmission Plc and facilitating a co-ordinated approach to the programme, land assembly, and the carrying out of the Peartree Hill Project works and the Wanlass Beck Project;
(c) providing a point of contact for continuing liaison and co-ordination throughout the construction and operation of the authorised works; and
(d) keeping National Grid Electricity Transmission Plc informed on the programme of works for the authorised works.

---
Source: https://www.legislation.gov.uk/uksi/2026/869/schedule/11/paragraph/56 (the official version)
Page: https://openlegislation.uk/peartree-hill-solar-farm-order-2026/schedule-11/paragraph-56
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.