  "url": "https://openlegislation.uk/peartree-hill-solar-farm-order-2026/schedule-11/paragraph-69",
  "json_url": "https://openlegislation.uk/peartree-hill-solar-farm-order-2026/schedule-11/paragraph-69.json",
  "legislation": "uksi/2026/869",
  "legislation_title": "The Peartree Hill Solar Farm Order 2026",
  "legislation_url": "https://openlegislation.uk/peartree-hill-solar-farm-order-2026",
  "path": "schedule/11/paragraph/69",
  "kind": "paragraph",
  "number": "69",
  "heading": null,
  "text": "If in consequence of the agreement reached in accordance with paragraphs 61(1) and 62(2) (Acquisition of Land) or the powers granted under this Order the access to any apparatus and/or the Wanlass Beck Site is materially obstructed, the undertaker must provide such alternative means of access to such apparatus and/or the Wanlass Beck Site as will enable National Grid Electricity Transmission Plc to access, maintain or use the apparatus and/or the Wanlass Beck Site no less effectively than was possible before such obstruction.",
  "extent": null,
  "status": null,
  "version": "current",
  "annotations": [],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2026/869/schedule/11/paragraph/69",
    "retrieved_at": "2026-10-28T20:57:04.416898+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}