# The Peartree Hill Solar Farm Order 2026, Paragraph 69


If in consequence of the agreement reached in accordance with paragraphs 61(1) and 62(2) (Acquisition of Land) or the powers granted under this Order the access to any apparatus and/or the Wanlass Beck Site is materially obstructed, the undertaker must provide such alternative means of access to such apparatus and/or the Wanlass Beck Site as will enable National Grid Electricity Transmission Plc to access, maintain or use the apparatus and/or the Wanlass Beck Site no less effectively than was possible before such obstruction.

---
Source: https://www.legislation.gov.uk/uksi/2026/869/schedule/11/paragraph/69 (the official version)
Page: https://openlegislation.uk/peartree-hill-solar-farm-order-2026/schedule-11/paragraph-69
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.