# The Peartree Hill Solar Farm Order 2026, Paragraph 70


Save for differences or disputes arising under paragraph 62(2), 62(4) 63(1) and 64 any difference or dispute arising between the undertaker and National Grid Electricity Transmission Plc under this Part of this Schedule must, unless otherwise agreed in writing between the undertaker and National Grid Electricity Transmission Plc, be determined by arbitration in accordance with article 48 (arbitration).

---
Source: https://www.legislation.gov.uk/uksi/2026/869/schedule/11/paragraph/70 (the official version)
Page: https://openlegislation.uk/peartree-hill-solar-farm-order-2026/schedule-11/paragraph-70
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.