# The Peartree Hill Solar Farm Order 2026, Paragraph 71


Any plans submitted to National Grid Electricity Transmission Plc by the undertaker pursuant to this Part must be submitted using the LSBUD system (https://lsbud.co.uk/) or to such other address as National Grid Electricity Transmission Plc may from time to time appoint instead for that purpose and notify to the undertaker in writing.

---