# The Peartree Hill Solar Farm Order 2026, Paragraph 21: Further information regarding requirements


(1) In relation to any application made under this Schedule 2, the local planning authority may request such further information from the undertaker as it considers necessary to enable it to consider the application.
(2) In the event the local planning authority considers such further information to be necessary and the requirement concerned contained in Part 1 of this Schedule does not specify that consultation with a consultee is required, the local planning authority must, within 15 business days of receipt of the application, notify the undertaker in writing specifying the further information required and (if applicable) to which part of the application it relates.
(3) In the event that the local planning authority does not give such notification within the period specified in sub-paragraph (2) or (4) the local planning authority (and the consultee, as the case may be) is deemed to have sufficient information to consider the application and is not subsequently entitled to request further information without the prior agreement of the undertaker.
(4) If the requirement concerned contained in Part 1 of this Schedule specifies that consultation with a consultee is required, the local planning authority must issue the application to the consultee within 14 days of receipt of the application, and notify the undertaker in writing specifying any further information requested by the consultee within 14 days of receipt of such a request.

---
Source: https://www.legislation.gov.uk/uksi/2026/869/schedule/2/paragraph/21 (the official version)
Page: https://openlegislation.uk/peartree-hill-solar-farm-order-2026/schedule-2/paragraph-21
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.