Paragraph 4 Construction environmental management plan
No part of the authorised development may commence until a CEMP for that part has been submitted to and approved by the local planning authority, following consultation by the undertaker with the Environment Agency on matters relevant to its respective functions and Natural England in relation to measures associated with bentonite breakout only.
Any CEMP submitted must include a commitment to regularly share all relevant pre-construction, construction, post-construction and operational survey and monitoring data in the appropriate formats with the relevant Local Environmental Records Centre(s) and relevant national and regional environmental recording schemes.
Any CEMP submitted for approval under sub-paragraph (1) must be in accordance with the outline CEMP.
The construction of any part of the authorised development must be carried out in accordance with the approved CEMP for that part.