# The Peartree Hill Solar Farm Order 2026, Paragraph 5: Construction traffic management plan


(1) No part of the authorised development may commence until a CTMP for that part has been submitted to and approved by the local planning authority, following consultation by the undertaker with Hull City Council and National Highways on matters relevant to their respective functions.
(2) Any CTMP submitted for approval under sub-paragraph (1) must be in accordance with the outline CTMP.
(3) The construction of any part of the authorised development must be carried out in accordance with the approved CTMP for that part.

---