  "heading": "Battery safety management plan",
  "text": "(1) No part of the authorised development that contains Work No. 2 may commence until a BSMP for that part has been submitted to and approved by the local planning authority, following consultation by the undertaker with the Humberside Fire and Rescue Service and the Environment Agency on matters relevant to their respective functions.\n(2) Any BSMP submitted for approval under sub-paragraph (1) must be in accordance with the outline BSMP.\n(3) Any BSMP approved under sub-paragraph (1) must be implemented as approved and maintained throughout the construction, operation and decommissioning of Work No. 2.",
  "extent": null,
  "status": null,
  "version": "current",
  "annotations": [],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2026/869/schedule/2/paragraph/8",
    "retrieved_at": "2026-10-28T20:57:04.416898+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}