# The Pension Schemes (Information Requirements — Qualifying Overseas Pension Schemes, Qualifying Recognised Overseas Pensions Schemes and Corresponding Relief) Regulations 2006, Regulation 3AG: Provision of information about liability for overseas transfer charge


(1) If an onward transfer is made from a QROPS or former QROPS and the overseas transfer charge arises on the transfer, the scheme manager of the QROPS or former QROPS must within 90 days after the date of the transfer provide the member with a notice stating—
(a) the date of the transfer,
(b) that overseas transfer charge arises on the transfer,
(ba) whether the charge arises under section 244AC or section 244IA,
(bb) whether the transfer is a transfer of the kind mentioned in section 244IA(1)(a) and, if so, the amount of the member’s overseas transfer allowance used up by the transfer,
(c) the transferred value of the transfer,
(d) the amount of the charge on the transfer,
(e) whether, and to what extent, the scheme manager has accounted, or intends to account, for the charge, and
(f) where the scheme manager has accounted for the charge, the date the scheme manager did so.
(2) If an onward transfer is made from a QROPS or former QROPS and the transfer is excluded from the overseas transfer charge by or under sections 244B to 244H, the scheme manager of the QROPS or former QROPS must within 90 days after the date of the transfer provide the member with a notice stating—
(a) the date of the transfer,
(b) that the transfer is excluded from the overseas transfer charge,
(c) the provision by reason of which the transfer is excluded, and
(d) where that provision is section 244B ...—
(i) when the relevant period for the transfer ends, and
(ii) how the transfer may turn out not to be excluded as a result of the member changing country or territory of residence within the relevant period for the transfer.
(3) Paragraph (4) applies if—
(a) a recognised transfer is made to a QROPS, or
(b) an onward transfer is made by a QROPS or former QROPS.
(4) Where an event occurring before the end of the relevant period for the transfer (see the definition of “the relevant period” in section 244AB(1)) means that the transfer no longer counts as excluded from the overseas transfer charge or that entitlement to repayment under section 244M arises, the scheme manager of the QROPS or former QROPS must, within 90 days after the date the scheme manager is notified of the event, provide the member with a notice stating—
(a) the amount of overseas transfer charge on the transfer,
(b) whether, and to what extent, the scheme manager has accounted, or intends to account, for the charge, and
(c) where the scheme manager has accounted for the charge, the date the scheme manager did so.
(5) Paragraph (6) applies if—
(a) a relieved relevant non-UK scheme transfer is made to a QROPS, and
(b) an event occurs before the end of the relevant period for the transfer (see the definition of “the relevant period” in section 244AB(1)) that means that the transfer no longer counts as excluded from the overseas transfer charge or that entitlement to repayment under section 244M arises.
(6) The scheme manager of the QROPS or former QROPS must, within 90 days after the date the scheme manager is notified of the event, provide the member with a notice stating the amount of the overseas transfer charge on the transfer.

---
Source: https://www.legislation.gov.uk/uksi/2006/208/regulation/3AG (the official version)
Page: https://openlegislation.uk/pension-schemes-information-requirements-qualifying-overseas-pension-schemes-qualifying-recognised-overseas-pensions-schemes-and-corresponding-relief-regulations-2006/regulation-3AG
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.