  "heading": "Electricity transmission systems: extension of commissioning period",
  "text": "In section 6G(1) of the Electricity Act 1989 (meaning of “commissioning period” for the purposes of determining whether a person is to be regarded as participating in the transmission of electricity), in paragraph (b), for “18 months” substitute “27 months”.",
  "extent": "E+W",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "S. 28 in force at 18.2.2026, see s. 118(1)(o)"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/ukpga/2025/34/section/28",
    "retrieved_at": "2026-11-04T03:49:26.153791+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}