Where the council or, as the case may be, the Department determines or, following a hearing by the Commission, confirms that an environmental statement is required, it shall be submitted to the Commission within 6 months from the date of the determination or such extended period as may be agreed in writing between the appellant and the Commission and if not so submitted the deemed application and the ground (a) appeal (if any) shall elapse at the end of that period.

---