# Planning (Northern Ireland) Order 1972, Article 68: Compensation where planning permission required under this Order but not under the Act of 1944

Extent: N.I.

(1) This Article shall apply—
(a) where the development of land was permitted before 1st October 1973 by virtue of Article 4 of, and paragraph 5 of the Schedule to, the Planning (Interim Development) Order (Northern Ireland) 1944 SRO 1944/58 (development by mining undertakers); or
(b) where by virtue of section 9(1)(i) of the Act of 1944, the erection before 1st October 1973 of certain buildings for the purpose of agriculture did not constitute development,
if in either such case, by virtue of the Planning Act , planning permission is required, and that permission is refused or granted subject to conditions.
(2) In a case falling within paragraph (1), section 26 of the Act of 1965 shall apply as if—
(a) planning permission had been granted for the development; and
(b) on the date of the planning decision in question that permission had been revoked or modified under Article 29.

---
Source: https://www.legislation.gov.uk/nisi/1972/1634/article/68 (the official version)
Page: https://openlegislation.uk/planning-northern-ireland-order-1972/article-68
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.