(1) The maximum penalty that infrastructure-levy regulations can specify for an offence they create is—
(a) for a summary-only offence—
(i) a fine not exceeding level 5 on the standard scale,
(ii) a term of imprisonment not exceeding 12 months, or
(iii) both,
(b) for an either-way offence—
(i) a fine, which may not exceed the statutory maximum on summary conviction,
(ii) a term of imprisonment not exceeding—
(A) 12 months on summary conviction,
(B) 2 years on conviction on indictment, or
(iii) both.
(2) In sub-paragraph (1)(b), “either-way offence” means an offence that is triable either on indictment or summary complaint.

---