# The Pollution Prevention and Control (Industrial Emissions) Regulations (Northern Ireland) 2013, Paragraph 8: Cost-benefit analysis


The application for a variation of the conditions of the permit required by paragraph 7 must be accompanied by a cost-benefit analysis that assesses the cost and benefits of utilising the waste heat to satisfy economically justified demand, including through cogeneration, and of the connection of that installation to a district heating and cooling network.

---
Source: https://www.legislation.gov.uk/nisr/2013/160/schedule/13A/paragraph/8 (the official version)
Page: https://openlegislation.uk/pollution-prevention-and-control-industrial-emissions-regulations-northern-ireland-2013/schedule-13A/paragraph-8
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

