# The Pollution Prevention and Control (Industrial Emissions) Regulations (Northern Ireland) 2013, Paragraph 9: Cost-benefit analysis


An application to an enforcing authority under regulation 10 for a permit to operate a new installation with a total net thermal input exceeding 20 megawatts which forms part of a new or existing district heating and cooling network must be accompanied by a cost-benefit analysis that assesses the cost and benefits of utilising the waste heat from nearby installations.

---