Construction plant, concrete batching and aggregate plants, temporary grading, washing and weighing plant, temporary bridges, conveyor systems, temporary accesses, temporary buildings and offices and working spaces and residential caravans are only permitted to facilitate the construction or maintenance of the works and for no other purpose and shall be removed once the use for which they were installed has ceased.

---