OpenLegislation

Part 10 Otters

Changes not yet applied. Later legislation changes this provision in ways not yet written into the text below:

To prevent or minimise harm being caused by the construction of any of the authorised works to otters living within, or within the vicinity of, the port limits, the Company shall secure that during the period of the construction of the authorised works–

(a)

all pipelines are closed off and all open trenches ramped over in at least one position at the end of each working day throughout the period of the construction of the authorised works;

(b)

any new roadside fence which is to be erected within 50 metres of the Claddy House Burn shall continue to a depth of 200 millimetres below soil level; and

(c)

similar otter proof fencing is erected where reasonably practicable to exclude otters from the port limits.