The Port of Tilbury (Expansion) Order 2019f1 (“the Port of Tilbury Order”), which granted development consent within the meaning of the Planning Act 2008f2 (“the Act”) contained correctable errors within the meaning of paragraph 1(3) of Schedule 4 to the Actf3.

In accordance with paragraph 1(5)(a) of Schedule 4 to the Act, before the end of the relevant period as defined in paragraph 1(6)(a) of Schedule 4 to the Act, the Secretary of State received a request in writing from the applicantf4 for the correction of errors in the Port of Tilbury Order.

In accordance with paragraph 1(7) of Schedule 4 to the Act the Secretary of State informed the relevant local planning authority for the area in which the land to which the Port of Tilbury Order relates is situated that the request has been received.

The Secretary of State, in exercise of the powers conferred by section 119 of, and paragraph 1(4) and (8) of Schedule 4 to, the Act, makes the following Order.

Annotations

Footnotes

f1

S.I. 2019/359.

f2

2008 c. 29.

f3

Paragraph 1 of Schedule 4 was amended by section 128(2) of, and paragraphs 1 and 70 of Schedule 13 to, the Localism Act 2011 (c. 20). There are other amendments to paragraph 1 that are not relevant to this Order.

f4

The term “applicant” is defined in paragraph 4 of Schedule 4 to the Planning Act 2008.