  "url": "https://openlegislation.uk/port-talbot-steelworks-generating-station-order-2015/article-22",
  "json_url": "https://openlegislation.uk/port-talbot-steelworks-generating-station-order-2015/article-22.json",
  "legislation": "uksi/2015/1984",
  "legislation_title": "The Port Talbot Steelworks Generating Station Order 2015",
  "legislation_url": "https://openlegislation.uk/port-talbot-steelworks-generating-station-order-2015",
  "path": "article/22",
  "kind": "article",
  "number": "22",
  "heading": "Certification of plans, etc.",
  "text": "(1) The undertaker must, as soon as practicable after the making of this Order, submit to the Secretary of State copies of—\n(a) the book of reference (document 4.03 Rev1, April 2015);\n(b) the design and access statement (document 10.03, July 2014);\n(c) the design principles document (document DPD1.01, April 2015);\n(d) the environmental statement (documents 6.01 to 6.04.7, July 2014);\n(e) the land plans (document 2.03, July 2014); and\n(f) the works plans (document 2.04, July 2014),\nfor certification that they are true copies of the plans or documents referred to in this Order.\n(2) A plan or document so certified is admissible in proceedings as evidence of the contents of the document of which it is a copy.",
  "extent": "E+W+S",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Art. 22 in force at 30.12.2015, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2015/1984/article/22",
    "retrieved_at": "2026-10-28T23:29:34.498663+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}