# The Port Talbot Steelworks Generating Station Order 2015, Article 24: Procedure in relation to certain approvals, etc.

Extent: E+W+S

(1) Where an application is made to, or request is made of, the relevant planning authority, the highway authority or the owner of a watercourse, sewer or drain for any consent, agreement or approval required or contemplated by any of the provisions of this Order (including a Requirement), the consent, agreement or approval, if given, must be given in writing and must not be unreasonably withheld.
(2) Schedule 5 (procedure for discharge of Requirements) has effect in relation to all consents, agreements or approvals granted, refused or withheld in relation to the Requirements.

---