# The Port Talbot Steelworks Generating Station Order 2015, Paragraph 12: External lighting

Extent: E+W+S

(1) Not less than 3 months before commissioning any stage of the authorised development, the undertaker must submit to the relevant planning authority written details of all external lighting to be installed at that stage of the authorised development.
(2) The details must be in accordance with the environmental statement and the design and access statement and must include details of the direction and levels of lighting.
(3) The relevant stage of the authorised development must not be brought into operation until the details submitted under sub-paragraph (1) have been approved by the relevant planning authority and the approved external lighting scheme has been installed.
(4) The approved lighting scheme must be retained for the duration of the operation of the relevant stage of the authorised development.

---
Source: https://www.legislation.gov.uk/uksi/2015/1984/schedule/2/paragraph/12 (the official version)
Page: https://openlegislation.uk/port-talbot-steelworks-generating-station-order-2015/schedule-2/paragraph-12
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.