# The Port Talbot Steelworks Generating Station Order 2015, Paragraph 19: Construction compound

Extent: E+W+S

(1) No stage of the authorised development may be commenced until details for that stage of the size, layout and location of temporary buildings and structures forming Work No. 1B have been submitted to and approved by the relevant planning authority.
(2) The temporary buildings and structures forming Work No. 1B must be installed in accordance with the approved details.

---
Source: https://www.legislation.gov.uk/uksi/2015/1984/schedule/2/paragraph/19 (the official version)
Page: https://openlegislation.uk/port-talbot-steelworks-generating-station-order-2015/schedule-2/paragraph-19
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.