# The Port Talbot Steelworks Generating Station Order 2015, Paragraph 3: Stages of authorised development

Extent: E+W+S

(1) The authorised development must not be commenced until the undertaker has given a written notice to the relevant planning authority stating whether the authorised development is to be constructed in 1 stage or 2 stages.
(2) If the notice states that the authorised development is to be constructed in 2 stages, the notice must state the extent of the authorised development that is to be constructed in each stage, which must not exceed the maximum parameters set out in Requirement 4 (detailed design).
(3) The authorised development must be constructed in accordance with the number of stages specified in the notice.

---
Source: https://www.legislation.gov.uk/uksi/2015/1984/schedule/2/paragraph/3 (the official version)
Page: https://openlegislation.uk/port-talbot-steelworks-generating-station-order-2015/schedule-2/paragraph-3
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.