# The Port Talbot Steelworks Generating Station Order 2015, Paragraph 12: Co-operation

Extent: E+W+S

National Grid and the undertaker must each use their best endeavours to co-operate with the other party on the timing and method of execution of any works carried out under this Order in the interests of safety and the efficient and economic execution of the authorised development, taking into account the need to ensure the safe and efficient operation of the other party’s operations.

---