# The Port Talbot Steelworks Generating Station Order 2015, Paragraph 12: Arbitration

Extent: E+W+S

(1) Subject to sub-paragraph (2), differences or disputes arising between the undertaker and DCC under this Part must, unless otherwise agreed in writing, be determined by arbitration in accordance with article 25 (arbitration).
(2) Article 25 does not apply where DCC uses a warrant of entry in accordance with the Water Industry Act 1991.

---
Source: https://www.legislation.gov.uk/uksi/2015/1984/schedule/4/part/4/paragraph/12 (the official version)
Page: https://openlegislation.uk/port-talbot-steelworks-generating-station-order-2015/schedule-4/part-4/paragraph-12
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.