  "url": "https://openlegislation.uk/portishead-branch-line-metrowest-phase-1-order-2022/schedule-12",
  "json_url": "https://openlegislation.uk/portishead-branch-line-metrowest-phase-1-order-2022/schedule-12.json",
  "legislation": "uksi/2022/1194",
  "legislation_title": "The Portishead Branch Line (MetroWest Phase 1) Order 2022",
  "legislation_url": "https://openlegislation.uk/portishead-branch-line-metrowest-phase-1-order-2022",
  "path": "schedule/12",
  "kind": "schedule",
  "number": "12",
  "heading": "Land of which temporary possession may be taken",
  "text": "(1)\nLocation\n(2)\nNumber of land shown on land plan\n(3)\nPurpose for which temporary possession may be taken\n(4)\nRelevant part of the authorised development\nIn the District of North Somerset, Portishead\n01/70, 01/75, 01/76, 01/77\nWorking space and access for construction\nWork No. 2\nIn the District of North Somerset, Portishead\n01/91\nWorking space and access for construction\nWork No. 2A\nIn the District of North Somerset, Portishead\n01/111, 01/112\nAccess, working space, materials storage, compound and lay down area for construction\nWork Nos. 1, 7A and 7D\nIn the District of North Somerset, Portishead\n01/210\nAccess, working space for construction and ecological mitigation\nWork Nos. 1 and 7B\nIn the District of North Somerset, Portishead\n01/211, 01/212, 01/216\nAccess, working space for construction and ecological mitigation\nWork Nos. 1 and 7B\nIn the District of North Somerset, Portishead\n01/220, 01/221, 01/230, 01/231, 01/232\nAccess, working space and materials storage, compound, lay down area for construction and diversionary route for path\nWork Nos. 1 and 7D\nIn the District of North Somerset, Portishead\n01/222\nAccess, working space for construction\nWork Nos. 1, 5, 7A and 7D\nIn the District of North Somerset, Portishead\n01/226\nAccess, working space, and ecological mitigation for construction\nWork Nos. 1, 5 and 7A\nIn the District of North Somerset, Portishead\n01/240, 01/241, 01/250\nAccess, working space for construction and ecological mitigation\nWork No. 1\nIn the District of North Somerset, Portishead\n01/251, 01/265\nAccess, working space for construction and diversionary route for path\nWork No. 1\nIn the District of North Somerset, Portishead\n01/296, 01/297\nAccess, working space for construction and ecological mitigation\nWork No. 1\nIn the District of North Somerset, Portishead\n01/310\nAccess, haul road, materials storage and working space for construction\nWork Nos. 1, 1A, 1B, 1C and 8\nIn the District of North Somerset, Portbury\n02/05, 02/06, 02/07, 02/08, 02/10, 02/20 02/26, 02/27\nAccess and ecological mitigation\nWork No. 1\nIn the District of North Somerset, Portbury\n02/30\nAccess, working space for construction and ecological mitigation\nWork Nos. 1 and 9\nIn the District of North Somerset, Portbury\n02/31, 02/32\nAccess and ecological mitigation\nWork No. 1\nIn the District of North Somerset, Portbury\n02/35\nTemporary construction compound and materials storage\nWork Nos. 1, 9 and 10A\nIn the District of North Somerset, Portbury\n02/36, 02/37\nTemporary diversion of permissive cycle path\nWork Nos .9 and 10A\nIn the District of North Somerset, Portbury\n02/40, 02/41, 02/45, 02/46, 02/75, 02/76, 02/82\nAccess, construction haul road, material storage and ecological mitigation works\nWork Nos. 1, 1A, 1B, 1C and 8\nIn the District of North Somerset, Portbury\n02/60, 02/65, 02/120\nAccess, haul road, material storage and working space for construction\nWork Nos. 1, 1A, 1B, 1C and 11A\nIn the District of North Somerset, Portbury\n02/85, 02/122\nAccess, haul road, visibility splays and working space for construction\nWork Nos. 1, 1A, 1B, 1C and 11A\nIn the District of North Somerset, Portbury\n02/116\nworking space and access for construction and ecological mitigation\nWork No. 1\nIn the District of North Somerset, Portbury\n02/118\nworking space and access for construction and ecological mitigation\nWork No. 1\nIn the District of North Somerset, Portbury\n02/145\nAccess, materials storage, temporary construction compound and working space\nWork Nos. 1, 1A, 1B, 1C, 7, 12, 12A, 20A and 22\nIn the District of North Somerset, Portbury\n02a/10, 02a/15\nAccess, haul road visibility splays and working space\nWork Nos. 8, 11 and 11A\nIn the District of North Somerset, Portbury\n02b/05\nAccess, materials storage, temporary construction compound and working space\nWork Nos. 1, 1A, 1B, 1C, 7, 12, 12A, 20A and 22\nIn the District of North Somerset, Portbury\n03/10\nAccess, materials storage, temporary construction compound and working space\nWork Nos. 1, 1A, 1B, 1C, 7, 12, 12A, 20A and 22\nIn the District of North Somerset, Portbury\n03/21\nAccess, working space and environmental mitigation works\nWork No. 1\nIn the District of North Somerset, Portbury\n03/35, 03/36, 03/37, 03/38\nAccess and environmental mitigation works\nWork No. 1\nIn the District of North Somerset, Portbury\n03/47, 03/67, 03/68\nAccess, working space and environmental mitigation works\nWork No. 1\nIn the District of North Somerset, Portbury\n03/65\nWorking space and works to adjacent disused station platform\nWork No. 1\nIn the District of North Somerset, Portbury\n03/71, 03/76\nAccess, material storage, working space and environmental mitigation\nWork No. 1A\nIn the District of North Somerset, Portbury\n03/80\nAccess, working space and visibility splay\nWork No. 1A\nIn the District of North Somerset, Portbury\n04/06, 04/07, 04/08\nAccess, working space and environmental mitigation\nWork No. 1A\nIn the District of North Somerset, Portbury\n04/10, 04/13, 04/15\nAccess, material storage, working space and environmental mitigation\nWork No. 1A\nIn the District of North Somerset, Portbury\n04/20\nAccess, turning space, materials storage, working space and environmental mitigation\nWork Nos. 1, 1A, 1B, 1C and 13\nIn the District of North Somerset, Portbury\n04/25, 04/46\nAccess, visibility splays, working space and environmental mitigation\nWork No. 13\nIn the District of North Somerset, Portbury\n04/41\nAccess, visibility splays, working space and environmental mitigation\nWork No. 13\nIn the District of North Somerset, Portbury\n04/42\nAccess, working space, materials storage and environmental mitigation\nWork Nos. 1, 1A, 1B, 1C and 13\nIn the District of North Somerset, Portbury\n04/55\nWorking space and vegetation clearance\nWork No. 14\nIn the District of North Somerset, Easton in Gordano\n04/90\nWorking space and vegetation clearance\nWork Nos. 1A, 14A and 14B\nIn the District of North Somerset, Easton in Gordano\n04/105\nWorking space and vegetation clearance\nWork No. 1A\nIn the District of North Somerset, Easton in Gordano\n05/10\nWorking space, access and vegetation clearance\nWork Nos. 1A and 15\nIn the District of North Somerset, Easton in Gordano\n05/17, 05/18\nAccess to works\nWork Nos. 1, 1A, 16, 16A, 16C, 17, 18, 19, 20A and 22\nIn the District of North Somerset, Easton in Gordano\n05/25, 05/106\nAccess and vegetation clearance\nWork Nos. 1, 1A, 16, 16A, 16C, 17, 18, 19, 20A and 22\nIn the District of North Somerset, Easton in Gordano\n05/26, 05/28\nWorking space, access and vegetation clearance\nWork Nos. 1, 1A, 16, 16A, 16C, 17, 18, 19, 20A and 22\nIn the District of North Somerset, Easton in Gordano\n05/113\nWorking space, access and vegetation clearance\nWork Nos. 1, 1A, 16, 16A, 16C, 17, 18, 19, 20A and 22\nIn the District of North Somerset, Easton in Gordano\n05/150, 05/152\nAccess, materials storage, temporary construction compound and working space\nWork Nos. 1, 1A, 1B, 1C, 16, 16A, 16C, 17, 17A, 18, 20A and 22\nIn the District of North Somerset, Easton in Gordano\n05/170\nTemporary construction compound, materials storage\nWork Nos. 1, 1A, 1B, 1C, 16, 16A, 16C, 18, 19, 20A and 22\nIn the District of North Somerset, Lodway\n06/15\nWorking space, access and vegetation clearance\nWork No. 1A\nIn the District of North Somerset, Lodway\n06/30\nAccess, materials storage, temporary construction compound and working space\nWork Nos. 1, 1A, 1B, 1C, 16, 16A, 16C, 17, 17A, 18, 20A and 22\nIn the District of North Somerset, Lodway\n06/35,06/36, 06/40, 06/45, 06/50, 06/65\nWorking space and access to works\nWork Nos. 1A, 1B, 1C, 17, 17A, 18 and 20A\nIn the District of North Somerset, Pill\n06/60, 06/105\nWorking space, oversail for crane and access to works\nWork Nos. 1B, 1C, 20, 20A and 20B\nIn the District of North Somerset, Pill\n06/61, 06/62, 06/63\nTemporary diversion of cycle path\nWork Nos. 1B, 1C, 20, 20A and 20B\nIn the District of North Somerset, Pill\n06/70, 06/75, 06/85, 06/90, 06/95, 06/100, 06/140, 06/145, 06/155\nWorking space and access to works\nWork Nos. 1B, 1C, 20A and 20B\nIn the District of North Somerset, Pill\n06/190\nAccess to works\nWork Nos. 1B, 1C, 20A and 20B\nIn the District of North Somerset, Pill\n06/532, 06/535\nWorking space and access to works\nWork Nos. 22A and 22B\nIn the District of North Somerset, Pill\n06/533\nTemporary compound\nWork Nos. 22A and 22B\nIn the District of North Somerset, Pill\n06/550, 06/555, 06/556\nAccess to Works\nWork Nos. 1B, 1C and 22\nIn the District of North Somerset, Pill\n06/596, 06/597, 06/598\nAccess to Works, demolition and replacement of wall\nWork Nos. 1B, 1C and 20A\nIn the District of North Somerset, Pill\n06/632, 06/633, 06/636\nAccess to Works\nWork Nos. 1B and 1C\nIn the District of North Somerset, Pill\n06/647, 06/661, 06/666, 06/705, 06/710, 06/730\nWorking space and access to works\nWork Nos. 1B and 1C\nIn the District of North Somerset, Pill\n07/05, 07/10, 07/15, 07/20, 07/25, 07/30, 07/35, 07/36, 07/44, 07/46, 07/51, 07/52, 07/53, 07/55, 07/56, 07/58, 07/59, 07/60, 07/65, 07/70, 07/80, 07/85, 07/90, 07/100, 07/105, 07/110, 07/111, 07/112, 07/113, 07/114, 07/116, 07/117, 07/121\nWorking space access to works and embankment strengthening\nWork Nos. 1B and 1C\nIn the District of North Somerset, Ham Green\n08/11, 08/20, 08/26\nWorking space and access to works\nWork Nos. 24 and 24A\nIn the District of North Somerset, Ham Green\n08/21, 08/22, 08/23, 08/24\nAccess to works\nInstallation of fencing and minor works to Parson Street to Royal Portbury Dock railway\nIn the District of North Somerset, Pill\n08/50, 08/60, 08/61\nAccess to works\nWork Nos. 24 and 24A\nIn the District of North Somerset, Abbots Leigh\n08/71\nAccess to works and materials storage\nInstallation of fencing and minor works to Parson Street to Royal Portbury Dock railway\nIn the District of North Somerset, Abbots Leigh\n09/11\nAccess to works and materials storage\nInstallation of fencing and minor works to Parson Street to Royal Portbury Dock railway\nIn the District of North Somerset, Abbots Leigh\n09/20\nAccess to works and materials storage\nStorage of materials, installation of fencing and minor works to Parson Street to Royal Portbury Dock railway\nIn the District of North Somerset, Abbots Leigh\n09/22, 09/23, 09/25\nAccess to works\nInstallation of fencing, works to retaining walls and minor works to Parson Street to Royal Portbury Dock railway\nIn the District of North Somerset, Abbots Leigh\n10/06\nAccess to works\nInstallation of fencing, works to retaining walls and minor works to Parson Street to Royal Portbury Dock railway\nIn the City and County of Bristol, Abbots Leigh\n10/11\nAccess to works\nInstallation of fencing, works to retaining walls and minor works to Parson Street to Royal Portbury Dock railway\nIn the City and County of Bristol, Abbots Leigh\n10/25\nAccess to works\nInstallation of fencing, works to retaining walls and minor works to Parson Street to Royal Portbury Dock railway\nIn the District of North Somerset, Abbots Leigh\n10/30\nAccess to works\nInstallation of fencing, works to retaining walls and minor works to Parson Street to Royal Portbury Dock railway\nIn the District of North Somerset, Abbots Leigh\n10/35\nAccess to works, rock picking, rock bolting, vegetation clearance, working space and environmental mitigation\nVegetation clearance, rock bolting and rock picking for the protection of the adjacent Parson Street to Royal Portbury Dock railway, ecological mitigation, installation of fencing and access for minor works, ecological mitigation\nIn the District of North Somerset, Abbots Leigh\n11/06\nAccess to works, rock picking, rock bolting, vegetation clearance, working space and environmental mitigation\nVegetation clearance, rock bolting, and rock picking for the protection of the adjacent Parson Street to Royal Portbury Dock railway, ecological mitigation, installation of fencing and access for minor works\nIn the District of North Somerset, Abbots Leigh\n11/07\nAccess to works working space and environmental mitigation\nAccess for vegetation clearance and rock picking for the protection of the Parson Street to Royal Portbury Dock railway, ecological mitigation\nIn the City and County of Bristol, Abbots Leigh\n11/10, 11/15\nAccess to works and working space\nInstallation of fencing, works to retaining walls and minor works to Parson Street to Royal Portbury Dock railway, ecological mitigation\nIn the City and County of Bristol, Abbots Leigh\n11/20\nAccess to works and working space\nInstallation of fencing, works to retaining walls and minor works to Parson Street to Royal Portbury Dock railway, ecological mitigation\nIn the City and County of Bristol, Abbots Leigh\n11/25\nAccess to works and working space\nInstallation of fencing, works to retaining walls and minor works to Parson Street to Royal Portbury Dock railway, ecological mitigation\nIn the District of North Somerset, Abbots Leigh\n11/41, 11/42\nAccess to works, rock picking, rock bolting, vegetation clearance, working space and environmental mitigation\nVegetation clearance, rock bolting and rock picking for the protection of the adjacent railway, installation of fencing and access for minor works to Parson Street to Royal Portbury Dock railway, ecological mitigation\nIn the District of North Somerset, Abbots Leigh\n11/61\nAccess to works\nVegetation clearance and rock picking for the protection of Parson Street to Royal Portbury Dock railway, ecological mitigation\nIn the District of North Somerset, Abbots Leigh\n11/65, 11/70, 11/75,\nAccess to works\nVegetation clearance and rock picking for the protection of Parson Street to Royal Portbury Dock railway, ecological mitigation\nIn the District of North Somerset, Abbots Leigh\n11/80\nAccess to works, rock picking, rock bolting, vegetation clearance, working space and environmental mitigation\nVegetation clearance, rock bolting and rock picking for the protection of the adjacent railway, installation of fencing and access for minor works to Parson Street to Royal Portbury Dock railway, ecological mitigation\nIn the District of North Somerset, Abbots Leigh\n11a/05\nAccess to works, rock picking, rock bolting, vegetation clearance, working space and environmental mitigation\nVegetation clearance, rock bolting and rock picking for the protection of Parson Street to Royal Portbury Dock railway, ecological mitigation\nIn the District of North Somerset, Abbots Leigh\n11a/10, 11a/15\nAccess to works\nAccess for vegetation clearance and rock picking for the protection of the Parson Street to Royal Portbury Dock railway, ecological mitigation\nIn the District of North Somerset, Abbots Leigh\n11b/05, 11b/10, 11b/15, 11b/20, 11b/30, 11b/35\nAccess to works\nAccess for vegetation clearance and rock picking for the protection of the Parson Street to Royal Portbury Dock railway, ecological mitigation\nIn the District of North Somerset, Abbots Leigh\n11b/25\nAccess to works\nMicro compound, access for vegetation clearance and rock picking for the protection of the Parson Street to Royal Portbury Dock railway, ecological mitigation\nIn the District of North Somerset, Abbots Leigh\n11c/05, 11c/10, 11c/15\nAccess to works\nAccess for vegetation clearance and rock picking for the protection of the Parson Street to Royal Portbury Dock railway, ecological mitigation\nIn the District of North Somerset, Abbots Leigh\n12/07 12/10, 12/20, 12/21, 12/30\nAccess to works, rock picking, rock bolting, vegetation clearance, working space and environmental mitigation\nWork No. 25 vegetation clearance, rock bolting and rock picking for the protection of the Parson Street to Royal Portbury Dock railway, ecological mitigation, installation of fencing and access for minor works to railway\nIn the City and County of Bristol, Abbots Leigh\n12/25\nAccess to works\nWork No. 25 Vegetation clearance, rock bolting and rock picking for the protection of the Parson Street to Royal Portbury Dock railway, ecological mitigation, installation of fencing and access for minor works to railway\nIn the District of North Somerset, Abbots Leigh\n13/07, 13/31, 13/32\nAccess to works, rock picking, rock bolting, vegetation clearance, working space and environmental mitigation\nVegetation clearance, rock bolting and rock picking for the protection of the Parson Street to Royal Portbury Dock railway, ecological mitigation, installation of fencing and access for minor works to railway\nIn the City and County of Bristol, Abbots Leigh\n13/33, 13/36, 13/40\nAccess to works\nWork No. 25 Vegetation clearance, rock bolting and rock picking for the protection of the Parson Street to Royal Portbury Dock railway, ecological mitigation, installation of fencing and access for minor works to railway\nIn the District of North Somerset, Abbots Leigh\n13/55\nAccess to works, rock picking, rock bolting, vegetation clearance, working space and environmental mitigation\nVegetation clearance, rock bolting and rock picking for the protection of the Parson Street to Royal Portbury Dock railway, ecological mitigation, installation of fencing and access for minor works to existing railway\nIn the District of North Somerset, Abbots Leigh\n14/05\nAccess to works, rock picking, rock bolting, vegetation clearance, working space and environmental mitigation\nVegetation clearance, rock bolting and rock picking for the protection of the Parson Street to Royal Portbury Dock railway, ecological mitigation\nIn the City and County of Bristol\n14/10, 14/25, 14/35\nAccess to works\nWork No. 25 Vegetation clearance, rock bolting and rock picking for the protection of the Parson Street to Royal Portbury Dock railway, ecological mitigation, installation of fencing and access for minor works to railway\nIn the City and County of Bristol\n15/15\nTemporary construction compound, materials storage and access to works\nWork Nos. 26 and 26A installation of fencing and access for minor works to Parson Street to Royal Portbury Dock railway\nIn the City and County of Bristol\n16/56, 16/57. 16/58, 16/61, 16/62, 16/63, 16/75, 16/80, 16/85\nAccess to works\nWork No. 28\nIn the City and County of Bristol\n17/05, 17/20\nTemporary construction compound, materials storage and access to works\nWork No. 29\nIn the City and County of Bristol\n17/10, 17/15\nAccess to works\nWork No. 29",
  "extent": "E+W",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 12 in force at 5.12.2022, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2022/1194/schedule/12",
    "retrieved_at": "2026-10-28T21:53:31.025268+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}