# The Portishead Branch Line (MetroWest Phase 1) Order 2022, Paragraph 125


The undertaker must repay to the Trust all costs, charges and expenses which it may reasonably incur or which it may sustain—
(a) in the examination of plans under this Part of this Schedule;
(b) in respect of the approval of plans submitted by the undertaker and the supervision by the Trust of the carrying out or construction of any activities or the Quarry Bridge 2 works and otherwise in connection with the implementation of the provisions of this Part of this Schedule; and
(c) in respect of the employment or procurement of the services of any persons whom it is reasonably necessary to appoint for inspecting and watching the activities of the undertaker on Trust property.

---
Source: https://www.legislation.gov.uk/uksi/2022/1194/schedule/16/paragraph/125 (the official version)
Page: https://openlegislation.uk/portishead-branch-line-metrowest-phase-1-order-2022/schedule-16/paragraph-125