# The Portishead Branch Line (MetroWest Phase 1) Order 2022, Paragraph 53


(1) The undertaker must present to BPC not less than three months before the intended date of commencing construction the draft programme for the execution of each part of the authorised development on BPC’s property.
(2) The undertaker must consult with BPC in relation to the draft programme and must present its final programme for the execution of the authorised development on BPC’s property to BPC not less than four weeks before the intended date of commencing construction.
(3) The undertaker must not enter on or take temporary possession of any part of BPC’s property unless it has served at least 14 days’ written notice on BPC of its intended entry onto that part.
(4) In this paragraph “intended date of commencing construction” means the first date on which the undertaker wishes to commence construction of any part of the authorised development on, under or over any part of BPC’s property, including carrying out any preparatory activities.
(5) In the exercise of any powers of temporary possession in respect of any part of BPC’s property and in the commencement and execution of the authorised development on BPC’s property the undertaker must—
(a) proceed diligently with the works affecting each part of BPC’s property; and
(b) notify BPC in writing of the completion of the relevant part of the authorised development affecting each part of BPC’s property within fourteen days of its completion.
(6) In the exercise of any powers of temporary possession in respect of any part of BPC’s property the undertaker must not—
(a) except with the agreement of BPC, provide or authorise the provision of car parking or storage (for materials or other items) facilities on any part of BPC’s property other than within Work No. 16A;
(b) demolish or remove any buildings; or
(c) except as BPC agrees, construct or carry out on BPC’s property any works comprising fencing, any mitigation works, ground or rock stability, geotechnical or strengthening works other than works which are of a temporary nature.
(7) In addition to and without limitation on the scope of the undertaker’s other obligations under this Order (including those in article 33(4) and Schedule 2), before giving up possession of any part of BPC’s property in respect of which any powers of temporary possession have been exercised the undertaker must remove any works constructed in contravention of sub-paragraph (6) or paragraph 54.

---
Source: https://www.legislation.gov.uk/uksi/2022/1194/schedule/16/paragraph/53 (the official version)
Page: https://openlegislation.uk/portishead-branch-line-metrowest-phase-1-order-2022/schedule-16/paragraph-53
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.