# The Portishead Branch Line (MetroWest Phase 1) Order 2022, Paragraph 7

Extent: E+W

The undertaker must—
(a) at all times afford reasonable facilities to the engineer for access to a specified work during its construction; and
(b) supply the engineer with all such information as the engineer may reasonably require with regard to a specified work or the method of constructing it.

---
Source: https://www.legislation.gov.uk/uksi/2022/1194/schedule/16/paragraph/7 (the official version)
Page: https://openlegislation.uk/portishead-branch-line-metrowest-phase-1-order-2022/schedule-16/paragraph-7
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.